Analysis: The recent Tennessee Court of Appeals
decision of Brooke Buttrey v.
Holloway's, Inc., No. M2011-01335-COA-R3-CV, 2012 WL 6451802 (Tenn. Ct. App.
December 12, 2012)
considered a case where the defendant failed to construct the home in a
workmanlike manner. The trial court
concluded the defendant breached its contract based on the deficiencies in the
construction of the home. The next
question was, what are the appropriate damages for the deficient work? The trial court found the defendant was
required to pay back the total amount the plaintiff paid to build her house,
$143,272.00. Buttrey at 4.
It is clear under Tennessee law that in a
breach of contract action, “damages resulting from the breach are a necessary
element of the claim and, therefore, the claimant has the burden of proving
damages at trial.” Buttrey at 7. Under Tennessee law the purpose of assessing
damages in a breach of contact case is to "make the non-breaching party
whole, to place the non-breaching party in the same position he would have been
in had the contract been performed."
Buttrey at 7. (citing Hiller
v. Hailey, 915 S.W.2d 800, 805 (Tenn. Ct. App. 1995)). As a result, the “damages awarded by the
trial court should have been designed to place Ms. Buttrey
in the position she would have been in had the contract been performed as contemplated." Buttrey at 7.
Tennessee courts have
adopted specific measures of damages in construction defect cases. This has been explained as follows:
As a general rule,
the measure of damages is the cost of correcting the defects or completing the
omissions, rather than the difference in value between what ought to have been
done in the performance of the contract and what has been done, where the
correction or completion would not involve unreasonable destruction of the work
done by the contractor and the cost thereof would not be grossly
disproportionate to the results to be obtained. On the other hand, the courts
generally adhere to the view that if a builder or contractor has not fully
performed the terms of the construction agreement, but to repair the defects or
omissions would require a substantial tearing down and rebuilding of the
structure, the measure of damages is the difference in value between the work
if it had been performed in accordance with the contract and that which was
actually done, or (as it is sometimes said) the difference between the value of
the defective structure and that of the structure if properly completed.
Buttrey at 8. (citing Edenfield
v. Woodland Manor, 462 S.W.2d 237, 241 (Tenn. Ct. App. 1970)).
As a result, under Tennessee law there are
basically two ways to measure damages: the cost of repair or diminution in
value. Buttrey at 8. Usually the only appropriate way to assess
damages is the cost of repair, however diminution in value can be used as a
measure of damages in certain limited circumstances. Buttrey at 8. The court stated that "[g]enerally, the
measure of damages will be the cost [of] repair unless the repairs are not
feasible or the cost is disproportionate to the [diminution] in value. If the cost of repairs is disproportionate
when compared with the difference in value of the structure actually
constructed and the one contracted for, the diminution value may be used
instead as the measure of damages.
Furthermore, ‘the burden is on the
defendant to show that the cost of repairs is unreasonable when compared to the
diminution in value due to the defects and omissions.” Buttrey at 8.
The court noted there is precedent under
Tennessee law for awarding a homeowner the price that was paid to have the
house built, however, the proof must include testimony the house currently has no
value or that the cost for repairing the house equals the amount paid to have
it built. Buttrey at 9. (citing Bowling v. Jones,
300 S.W.3d 288, 296 (Tenn. Ct. App. 2008)). In the Buttrey
case, there was no such proof in the record.
Further, the plaintiff has lived in the home since December of 2003 and
certainly there was value in living in the residence.
Ultimately, the appellate court found the
plaintiff failed to establish the cost of necessary repairs for the home. In fact at trial the only direct evidence for
the cost of repairs was approximately $36,766.17. Buttrey at 10. The appellate court therefore reviewed the
record in detail in order to determine if there were other additional repair
costs or specific damages. By examining
the record, the appellate court noted there was no specific evidence of the
dollar amounts to make additional repairs however it is clear additional
repairs were required. As a result, the
appellate court reduced the award from $143,272.00 to $73,532.34. It appears that the appellate court did its
best to review the trial court record in order to determine the correct amount
of damages.
This case shows how important it is to
make sure appropriate and proper proof of damages is presented at trial. Plaintiff has the burden to establish damages
as a part of the plaintiff's claim in a construction defect case. In this case, the damages may have been
higher however direct evidence and proof of damages was limited. As a result, the court was forced to
speculate and try to discern from the record the amount of the damages where insufficient
proof was offered to determine the amount of damages. Further, the appellate court rejected the
trial court's award providing the total cost of the contract as damages. This was due to the fact the plaintiffs have lived
in the home for almost ten years since construction so there was clearly some
value in the home and it was not completely worthless even though the work was not
performed in a workmanlike manner.
Follow me on Twitter at @jasonalee for updates from the Tennessee Defense Litigation
blog.
|