A recent decision by the Tennessee Court of Appeals in The Counts Co. v. Praters, Inc., E2011-01624-COA-R3-CV, 392 S.W.3d 80 (filed June 22, 2012) discussed the Statute of Repose for construction defect cases. This opinion can be found at http://www.tsc.state.tn.us/sites/default/files/countscoopn.pdf. In this case, a contractor, Praters, Inc., installed hardwood flooring at the request of the plaintiff. A certificate of occupancy was issued on May 15, 2006. Praters Inc. completed this work and issued a warranty on May 28, 2006. The hardwood flooring started to show warping soon after the flooring was installed Approximately one year after the installation (in April or May of 2007) Praters, Inc. resurfaced the floor to try to correct the condition. Praters, Inc. continued to provide additional advice about the flooring from 2007 through 2010. This included the assertion by Praters, Inc. that the floor problem would correct itself once the moisture problem was resolved. Apparently the problem did not resolve.
A lawsuit was not filed against Praters, Inc. until March 21, 2011, almost five years after the installation. As a result, the issue before the Court was whether the four year Statute of Repose found T.C.A. § 28-3-202 barred this construction defect claim. The Statute of Repose in T.C.A. § 28-3-202 provides:
All actions to recover damages for any deficiency in the design, planning, supervision, observation of construction, or construction of an improvement to real property, for injury to property, real or personal, arising out of any such deficiency, or for injury to the person or for wrongful death arising out of any such deficiency, shall be brought against any person performing or furnishing the design, planning, supervision, observation of construction, construction of, or land surveying in connection with, such an improvement within four (4) years after substantial completion of such an improvement.
(emphasis added). The key dispute between the parties was when the four years, referred to in this statute, begins to run (i.e. the date of substantial completion). The Appellate Court agreed with the trial court decision and decided the floor installation was “substantially complete” by, at the latest, May 28, 2006. The fact resurfacing of the floor was completed approximately one year after the installation did not extend the Statute of Repose. Further, the fact there were continued attempts to correct the floor for several years following the installation also did not extend the Statute of Repose. The court found that the date of the discovery of the defect and the fact ongoing repairs occurred do not change the date of “substantial completion."
The term "substantial completion" is a defined...
|