The recent Tennessee Court of Appeals
decision of Keith Gillis
v. Covenant Health, 2015 WL 3563034 (Tenn. Ct. App. 2015) discussed the
four year statute of repose found in T.C.A.
§ 28-3-202 for construction defect claims.
This statute of repose is a very good way to defeat many construction
defect claims in Tennessee. This particular
case dealt with a situation where a radiology facility at Methodist Hospital was
allegedly defectively constructed.
Specifically, the walls around the radiology facilities required a
certain amount of lead shielding but there was a portion of the walls that did
not contain the necessary lead shield to protect individuals from exposure to
excessive radiation. As a result,
plaintiffs claimed they were exposed to excessive radiation and therefore they sued
the construction company that failed to put in the necessary lead shielding.
Tennessee law is clear that we have a four year
statute of repose that bars claims for construction defect cases filed greater
than four years from the date of substantial completion (with certain
exceptions). The entire statute found in
T.C.A.
§ 28-3-202 is as follows:
All actions to
recover damages for any deficiency in the design, planning, supervision,
observation of construction, or construction of an improvement to real
property, for injury to property, real or personal, arising out of any such
deficiency, or for injury to the person or for wrongful death arising out of
any such deficiency, shall be brought against any person performing or
furnishing the design, planning, supervision, observation of construction,
construction of, or land surveying in connection with, such an improvement
within four (4) years after substantial completion of such an improvement.
The question therefore,
in many cases, centers around how to determine the date of “substantial
completion.” T.C.A.
§ 28-3-201(2) defines substantial completion as follows:
(2) “Substantial
completion” means that degree of completion of a project, improvement, or a
specified area or portion thereof (in accordance with the contract documents,
as modified by any change orders agreed to by the parties) upon attainment of
which the owner can use the same for the purpose for which it was intended; the
date of substantial completion may be established by written agreement between
the contractor and the owner.
In the Gillis
case, the plaintiffs argued, quite creatively, that the radiology facility was
not substantially complete because a necessary element of that facility (the
shielding in the wall) was missing.
Their argument was basically that the project could not be substantially
complete when there was such an important necessary element missing from the
project. They claimed that as a result,
the fact this case was filed approximately 8 years following the opening of the
facility did not bar the claim because the project was never “substantially
complete”. The trial court granted
summary judgment in favor of the defendants and that ruling was appealed.
On appeal, the
Tennessee Court of Appeals first considered the definition of substantial
completion. The Court noted “substantial
completion does not mean perfect completion according to the exact
specifications. Otherwise, the
qualifying word ‘substantial’ before ‘completion’ would have no meaning.” Gillis at 5. In this particular case the undisputed
evidence was that the emergency room department including the CT scan room at
issue was used from March 2006 until the suit was filed approximately eight
years later. The Tennessee Court of
Appeals found that plaintiffs’ argument would destroy the very purpose of the statute
of repose in Tennessee for construction defect cases. Under the plaintiffs’ theory, almost every construction
defect case could be brought without concern for the statute of repose because
the plaintiffs’ argument would basically require absolute perfect completion
before the four year statute of repose would begin to run. However, the Court noted the statute only
requires “substantial completion” where the resulting work is then used for its
intended purpose.
As a result, although
plaintiffs made a creative argument in this case to try to get around the statute
of repose, the Tennessee Court of Appeals found the trial court did not err
when it found that the date of substantial completion was in 2006. Therefore the statute of limitations applied
to bar this claim. The simple fact there
is outstanding work to be completed or that certain work was not performed as
required under the plans, does not extend the four years statute of
repose. This case correctly decided this
issue because if the court went the other way in this case, the construction
defect statute of repose would no longer have any teeth.
Follow me on Twitter at @jasonalee for updates from the Tennessee Defense Litigation
blog.
|